Schedule
Project will begin the last week of April. The south side of the road will be completed first. Storm sewers will be removed and upgraded followed by complete removal of curb and gutter. The road will be widened with new curb and gutter and then driveways will be restored and new sidewalk constructed. This work on the south side is expected to be complete in mid-July, after which the work will be shifted to the north side. Final project completion is scheduled for October 2021.